From the given plan in Fig. estimate the following quantities: (1) Earthwork for excavation (2) 2nd class brick masonry for foundation up to plinth (3) 1st class brick work for superstructure
[15 marks]Prepare abstract sheet for above example.
[5 marks]Which type of data are required for the estimation ? Write in details.
[5 marks]Write short note on (i) Typical Bay method, (ii) prime cost.
[5 marks]Explain Revised and Supplementary Estimate.
[5 marks]Explain the centerline method with suitable example.
[5 marks]Which IS code is referred for the various measurements? Write the deduction rules for plastering.
[5 marks]What is specification? Write the specification for the 1st class brickwork in CM (1:6) for superstructure.
[10 marks]Define tender. Give classifications of tender.
[5 marks]Workout the rate analysis for RCC (1:1.5:3) take quantity 10 m3.
[5 marks]What are the different types of contracts? Explain any one.
[5 marks]