State and explain the purpose of preparing estimate.
[3 marks]Write the formula for volume and surface area for the following shape: i. Cuboid ii. Sphere iii. Hemisphere iv. cylinder
[4 marks]For the Figure 1 find the quantities of following items of work by Long-wall Short-wall method. Earthwork in excavation in foundation trench i. Lime concrete in foundation ii. First class brick work in 1:6 cement mortar in foundation and plinth iii. 2.5 cm thick DPC (1:2:4) with water proofing compound The dimensions of doors, windows and selves are: Door D = 1.20 m × 2.10 m. Windows W = 1.00 m × 1.50 m Shelves S = 1.00 m × 1.50 m
[7 marks]What are the legal requirements o f a valid contract?
[3 marks]State the types of specifications. Describe General, Technical and Standard specifications.
[4 marks]Carry out the rate analysis for 1st Class Brickwork in Superstructure in Cement Mortar (1:4). Assume prevalent market rates for materials and labours.
[7 marks]Ahilly ground as shown in following figure has a cross-slope of 1 : 4 (V : H), and the proposed road formation, entirely in cutting, (1) – (2) – (3) – (4) has to be constructed. Calculate the area in cutting.1
[7 marks]Enlist the factors affecting the market rate of civil engineering materials.
[3 marks]Explain the advantages and disadvantages of an Item Rate Contract.
[4 marks]Draft a tender notice for Jungle cutting of road area and Tree plantation including one year free maintenance for a National Highway of your choice.
[7 marks]What Care would you take while drafting specifications?
[3 marks]What is meant by restricted specifications? What are the advantages and disadvantages of it?
[4 marks]Write detailed specification for RCC slab in M20.
[7 marks]Write short note on Scrutiny of tender.
[3 marks]Write some important Provisions of IS-1200 for working out quantities and deductions in civil works
[4 marks]Write detailed specification for earthwork.
[7 marks]Explain in brief about task work, sundry & work charge establishment.
[3 marks]Explain in brief earnest money deposit and Security deposit.
[4 marks]Provide the prevailing market rate of the following materials in your city: i. 10 mm diameter MS Bar, ii. Gully trap, iii. 53 grade Portland cement, iv. 20 mm nominal size coarse aggregate, v. 1st class bricks, vi. Kota stone, vii. Oil paint
[7 marks]Explain in detail termination of contract.
[3 marks]Write the detailed specification for the cement plaster in CM (1:6) on walls.
[4 marks]Abuilding costing Rs. 3, 50,000/- has recently been constructed in a big city. The plot measuring 450 sq. m was purchased @ Rs. 150/- per square meter. Work out the rent of the property. Assume 8% as net return on the cost of the construction and 4 1/2 % on the land value. All expected outgoing are Rs. 10000/- per year.
[7 marks]Discuss various types of estimates
[3 marks]Explain the factors affecting the value of property.
[4 marks]Enlist the various methods of valuation and explain any one in detail.2 FIGURE 1 PLAN DETAILS OF FOOTING3
[7 marks]