Determine volume of a frustum circular cone having base radius 0.6m, tip radius 0.3m and height 1.2m.
[3 marks]Compare revised estimate and supplementary estimate.
[4 marks]Enumerates and discuss various types of estimates.
[7 marks]Discuss accuracy criteria for concrete.
[3 marks]Determine volume of spherical segment having base 37cm, radius at top 35cm and height 25cm. take radius of sphere as 40cm.
[4 marks]Refer figure (a) and workout quantity of excavation.
[7 marks]Refer figure (a) and workout quantity of brickwork in foundation and plinth.
[7 marks]Write measurement unit of the Cement, Brickbats steel, and Oil paint Wood and Mosaic tiles.
[3 marks]Calculate the amount of cement and sand required for brick work in foundation and plinth from figure (a)
[4 marks]Discuss measurement method for road work.
[7 marks]Write the purposes of specifications.
[3 marks]Define rate analysis. How to fixed rate per unit of item in rate analysis?
[4 marks]Write specification for cement concrete work as shown in figure (a).
[7 marks]Discuss factor affecting the task work?
[3 marks]State the situation under which the need of arbitrator arises?
[4 marks]Calculate materials require for 10m3 of R.C.C. (1:2:4) slab work.
[7 marks]List condition of contract.
[3 marks]Give difference between Earnest money Deposit and Security Deposit.
[4 marks]Draft typical tender notice for civil engineering work.
[7 marks]Give difference between estimation and valuation.
[3 marks]Find out the yearly installment of loan of Rs. 50000 at rate of interest 12% is to be repaid in 15 years.
[4 marks]Write short note on scrutiny of tender.
[7 marks]Give difference between scrap value and salvage value.
[3 marks]Abuilding has monthly rent of 1500rs. Total outgoings are 20% of gross rent. Rate of interest on capital is 8%. Find capitalized value of building.
[4 marks]Discuss mode of payment to the contractor. How the first and final bill, running or interim bills are paid to contractor?1 Figure (a) PLAN 8.10 W W W W Room no 1 Room no 3.50 x 3.00 3.60 x3.00 D D 6.0 1.80 2.40 D Room no 3 2.40 W Ver. 1.50 1.50 3.60 1.80 Pillar 0.30 x 0.30 Steps All walls 30cm D 1.20 x 2.10 m W 1.20 x 1.35m W1 1.80 x1.35m SECTION OF A WALL R.C.C. SLAB 3.0 0.3 P L 0.40 0. 40 G GL 0.50 0.40 0.60 0.40 0.300 0.90 C.C.1:6:82
[2 marks]