Write formulas for the following: (1) Area of Segment of Circle (2) Volume of frustum of cone (3) Volume of sphere
[3 marks]Define following terms – Estimate, Contingencies, Spot Item, Prime Cost
[4 marks]For the following given figure a, calculate the quantities of following items by Centre line method
[7 marks]Earthwork in Excavation in foundation
[ marks]Cement Concrete bed in Foundation
[ marks]Brick masonry work in foundation up to plinth in cm 1:6.
[ marks]Discuss accuracy criteria for concrete
[3 marks]Compare revised estimate and supplementary estimate.
[4 marks]What is Contract? List out Various types of Special contract and explain Turnkey Contract in detail.
[7 marks]Enlist different types of tenders & explain anyone them
[7 marks]Provide the Prevailing market rate of the following materials in your city: 10 mm diameter MS Bar, Gully Trap, Kota Stone.
[3 marks]Define rate analysis. How we can fix rate per unit of item in rate analysis?
[4 marks]Calculate the following: 1. No. of bricks required for 5 cu. m. brickwork. 2. Materials required for M20 Grade of Concrete
[7 marks]Write short note on Schedule of rates (S.O.R) & Task of Work
[3 marks]Differentiate between Estimation & Valuation
[4 marks]Write short note on : 1. Scrutiny of tender 2. Classification of tender
[7 marks]Aperson requires Rs. 20000 after 5 years for the repair of his house. What amount he needs to invest at 7% to get required amount after said years?
[3 marks]What should be the amount of loan instalment if loan amount is Rs. 12,00,000 to be paid at annual interest rate of 13.78 % in 363 months
[4 marks]Calculate rent of newly constructed building from given data. 1) Cost of Land=7,00,000 , 2) Cost of Construction = 5,50,000 , 3) Total outgoings including sinking fund = 15.8 % of GI , 4) Net return @ 10% on construction and 5% on Land OR1
[7 marks]What do you mean by value? State the purposes of Valuation.
[3 marks]Differentiate between Earnest Money Deposit & Security Deposit.
[4 marks]Define the following terms: 1. Scrap value 2. Estimating 3. Cost 4. Salvage value 5. Book Value 6. Free hold property 7. Lease hold property
[7 marks]Explain following terms – Liquidated Damages, Unbalanced Tender, Arbitration
[3 marks]Discuss various reasons for rejection of the lowest tender.
[4 marks]Discuss mode of payment to the contractor. How the first and final bill, running or interim bills are paid to contractor?
[7 marks]Write difference between: 'Depreciation and Obsolescence.'
[3 marks]Define specification. What are the purpose of writing
[4 marks]Explain in brief various principles of writing good specifications Figure: a In figure: In section-AB consider data for section starting from pcc (from bottom) pcc : 0.9 m, of step 1: 0.6 m, of step 2: 0.5 m, of step 3: 0.4 m, wall : 0.2 m
[7 marks]