What is the project management? What are benefits from project management?
[3 marks]Write short note on types of project.
[4 marks]Write short note on project management functions.
[7 marks]How to estimate activity time of project?
[3 marks]Differentiate between PERT and CPM method.
[4 marks]Write short note on life-cycle phases of project planning.
[7 marks]Write short note on Bar (Gantt) Chart.
[7 marks]Write the importance of instrument index sheets.
[3 marks]What are responsibilities and duties of project manager in a project control?
[4 marks]Write short note on loop wiring diagram and process flow sheets.
[7 marks]Differentiate between pneumatic and electronic system.
[3 marks]Write design criteria for the flow measurement.
[4 marks]Classify hazardous locations as per NEC code.
[7 marks]Write various methods used for flow and pressure measurement.
[3 marks]Write various method used for temperature measurement. Explain any one with advantages.
[4 marks]Write the operating conditions for the selection of level measurement method? Explain any one level measurement method.
[7 marks]Classify control valve based on their function.
[3 marks]Discuss single and double seat construction of control valve .
[4 marks]Discuss control valve noise problem.
[7 marks]Which documents required for the efficient installation of instruments system?
[3 marks]Define startup time. What are problem faced during this time?
[4 marks]What is Loop check? Write check-out procedure for filled system temperature transmitter.
[7 marks]Define: (1) valve flow capacity Cv (2) rangeability (3) cavitation.
[3 marks]Discuss control valve flow characteristics.
[4 marks]Discuss ISO 9000 test standard and calibration. .
[7 marks]