Define and explain cost index. Also, state its usefulness.
[3 marks]What is a plant design project? Enlist the stages through which it moves to completion.
[4 marks]With special reference to Break-even point, Explain the factors affecting the estimation of investment and production cost.
[7 marks]Discuss types of flow diagrams in brief.
[3 marks]Write a note on types of valves and selection of valves.
[4 marks]State and discuss the factors to be considered in selection of the location of a chemical plant.
[7 marks]Define the terms: i) Book value ii) Service life iii) Salvage value
[3 marks]Explain types of depreciation according to their causes.
[4 marks]List and explain the items to be considered in estimation of total product cost.
[7 marks]Mention various methods for estimating capital investment.
[3 marks]List the items to be considered for estimating Fixed capital investment and working capital.
[4 marks]The original investment for an asset was Rs. 500000 and the asset was assumed to have a service life of 12 years with Rs. 100000 salvage value at the end of the service life. After the asset has been in use for 5 years, the remaining service life and final salvage value are re-estimated at 10 years and Rs. 50000, respectively. Under these conditions, what is the depreciation cost during the sixth year of the total life if straight-line depreciation is used?
[7 marks]Discuss any three safety aspects to be considered in a chemical plant project.
[3 marks]Differentiate between Standard and Special equipment.
[4 marks]What is BAR chart? Explain planning of a project schedule using it.
[7 marks]Differentiate between continuous process and batch process
[3 marks]Write a note on specification sheet of equipment.
[4 marks]Compare CPM and PERT techniques of project management.
[7 marks]Explain Importance of utility in chemical industry.
[3 marks]Write a short note on pipe fittings.
[4 marks]Discuss various practical factors of alternative investment and replacement decision.
[7 marks]State various waste treatment and disposal methods.
[3 marks]Explain the importance of laboratory development of Pilot plant.
[4 marks]Enlist various methods of Profitability analysis .Explain any two methods in detail.
[7 marks]