Explain stages of project planning.
[3 marks]Distinguish between CPM and PERT.
[4 marks]Explain various responsibilities of an engineer in a construction project.
[7 marks]Which are the objectives of material management?
[3 marks]Differentiate between standard equipment and special equipment.
[4 marks]How critical path is determined? What is float? Explain different types of floats.
[7 marks]Explain factors affecting the selection of construction equipment.
[7 marks]Which are the various levels of a work breakdown structure?
[3 marks]Differentiate between bar chart and milestone chart.
[4 marks]Discuss various network rules.
[7 marks]What different time estimates are used in PERT?
[3 marks]State the advantages of the line of balance technique.
[4 marks]Explain the logic of the precedence network. State advantages of precedence network.
[7 marks]State advantages of a good job layout.
[3 marks]Describe various sources of funds for a project.
[4 marks]Explain step by step process of resource smoothening and resource levelling.
[7 marks]What data is required for updating the network of a project?
[3 marks]Explain various BIM software.
[4 marks]Define: Direct cost, Indirect cost, Normal time, Crash time, Normal cost, Crash cost, and Cost slope.
[7 marks]Differentiate between quality control and quality assurance.
[3 marks]Explain elements of TQM.
[4 marks]Write a short note on Occupational Safety and Health Administration (OSHA).
[7 marks]Draw a line diagram of the power shovel excavator.
[3 marks]Explain the factors affecting the cycle time of a truck.
[4 marks]Write a short note on pile driving equipment.
[7 marks]