Define: Drought, Evapotranspiration, Ground water.
[3 marks]Enlist types of dams based on their function. Explain any one in brief.
[4 marks]What is hydrological cycle? Give a brief discussion of different components of hydrological cycle with neat sketch.
[7 marks]Enlist the types of Precipitation. Explain any one with neat sketch in brief.
[3 marks]Write shone note on Leeves and flood walls.
[4 marks]The recording rain gauge was installed on a basin having catchment area of 40 km2. The mass curve of rainfall is recorded during a storm is given below. If the volume of measured runoff due to storm is 1.35x106m3, estimate w-index and Ø-index of the basin. Consider start of storm in hours and cumulative rainfall in mm. Time from start of storm 0 2 4 6 8 10 12 14 16 Cumulative rainfall 0 7 19 58 70 85 93 99 102
[7 marks]Find out the ordinates of a storm hydrograph resulting from a 9 hr storm with rainfall of 2.0, 5.75 and 2.75 cm during subsequent 3-hr intervals. The ordinates of 3 hr UH at 3 hr interval are 0, 100, 355 ,510, 380, 300, 260, 225, 165, 120, 85, 55, 30,22,10,0 cumecs. Assume an initial loss of 0.5 cm, an infiltration index of 0.25cm/hr and a base flow of 10 cumecs.
[7 marks]Explain the terms with suitable example: Aquifuge, Aquiclude, Aquitard.
[3 marks]Afully penetrating well of diameter 0.5m is drilled in a confined aquifer 2.5m thick. If a steady state draw downs at 12m and 50m are observed to be 2.50m and 0.6m. Determine the discharge. Take k=1x10-3m/s.
[4 marks]Discuss the various methods of determining the average depth of rainfall over a catchment.
[7 marks]What is spillway? Explain function of spillway.
[3 marks]What is Darcy’s Law? How will you measure co-efficient of permeability of a soil?
[4 marks]Give difference between: (I) Hyetograph and Direct runoff hydrograph, (II) Unit hydrograph and S-Hydrograph.
[7 marks]Explain factors affecting the selection of site for a dam.
[3 marks]Give difference between Penstocks and Turbines.
[4 marks]Discuss with neat sketch, the various zones of reservoir.
[7 marks]Explain Ogee spillway and Chute spillway.
[3 marks]Define: (I) Safe yield, (II) Density current, (III) Trap efficiency, (IV) Useful life of a reservoir.
[4 marks]Write principle components of hydro electrical scheme and explain them with their utility.
[7 marks]Give difference between hydrological drought and meteorological drought.
[3 marks]Write short note on flood forecasting and warning.
[4 marks]Abridge has an expected life of 25 years and designed for flood management of return period of 100 years. (a) What is the risk of this hydrologic design? (b) If a 12% risk is acceptable, what return period will have to be adopted?
[7 marks]Explain various causes of flood.
[3 marks]Explain: (I) Hydrologic Storage routing, (II) Hydrologic channel routing.
[4 marks]What is Water harvesting? Explain various methods water harvesting.
[7 marks]