Write the factors influencing supply and demand of the product.
[3 marks]Explain in detail: Time value of money
[4 marks]Define the following terms: 1. Cost 2. Price 3. Spot Item 4. Prime Cost 5. Provisional Quantity 6. Salvage value 7. Scrap value
[7 marks]Write how approximate cost of construction can be calculated by using service unit method. Also write service units of various types of construction.
[3 marks]Give rules of deductions in plastering and pointing work.
[4 marks]For the figure-1 calculate the quantities of following items: 1) Excavation for foundation 2) Brick masonry work in foundation up to plinth in 1:6.
[7 marks]For the figure-1 calculate the quantities of following items: 1) Foundation Concrete 2) 12mm thick smooth plaster inside rooms and on ceiling in C.M. 1:3.
[7 marks]Write principles of writing specifications.
[3 marks]Explain requirements of a valid contract.
[4 marks]Write specification for R.C.C. work in 1:1.5:3 for slab.
[7 marks]What is specification? Write its necessity.
[3 marks]Differentiate between brief specifications and detailed specifications.
[4 marks]Define contract. Explain (I) Item rate contract (II) Material supply contract (III) Turn-key contract
[7 marks]Discuss factor affecting the task work?
[3 marks]Discuss various reasons for rejection of the lowest tender.
[4 marks]Give current market rate with measurement unit of following: Brick, Sand, Cement, Aggregate, Steel Bar and Lime. Also calculate quantity of material required for 10 m3 Brick Masonry in C.M. 1:4.
[7 marks]Write short note on S.O.R.
[3 marks]Explain in detail termination of contract.
[4 marks]Work out rate analysis for 15 mm thick cement plaster in C.M. 1:3.
[7 marks]Enlist different form of values and explain any two in brief.
[3 marks]Aperson purchased a land in 25,00,000 before 7 years. Presently value of same land is 40,00,000. Consider compound interest of 6% on Fixed deposit and calculate net profit to the owner of land.
[4 marks]From the following details find out the monthly rent of a property:1 Cost of land – 15,00,000, Cost of construction – 12,00,000, Expected returns on investment – 12%, Interest rate on sinking fund – 5%, Outgoings – 30% of gross rent, Expected life of the building – 30 years and scrap value = 15%.
[7 marks]Explain factors affecting value of property.
[3 marks]Differentiate between depreciation and obsolesce.
[4 marks]Amachine is purchased for Rs-1,25,000. Assuming its life 17 years and its salvage value 12%. Calculate the book value at the end of each year for years in a tabular form by using following methods: (1) Straight Line Method (2) Constant Percentage Method. Note: all dimension are in meter. Take 15cm lintel bearing. SCHEDULE OF OPENING Figure-12
[5 marks]