Explain methods for building estimates and explain any one in detail.
[6 marks]What is the significance of market survey? How the rate of an item is derived by method of rate analysis?
[4 marks]Define the term: 1. Tender fees 2. Ernest money deposit 3. Surface excavation, 4. Security deposit
[4 marks]Fig.1 shows the details of RCC beam. Calculate the following quantities. A, Total quantity of steel bars B, Quantity of form work C, Number of cement beg required D, Quantity of concrete work
[10 marks]The Fig.2 shows details of a residential building. Calculate the quantities of the following items. A, Earthwork in excavation for foundation B, Brick masonry up to plinth in c.m. 1:6. C, Smooth plaster inside the rooms and ceilings in c.m. 1:3.
[10 marks]Which IS code is referred for the various measurements? Write the deduction rules for plastering.
[5 marks]Give accuracy criteria for length, area and volume.
[5 marks]Find the rate of Plain cement concrete (1:1.5:3) per cu.m. by rate analysis. Assume suitable rates of material and labour.
[5 marks]Explain factors affecting rate analysis.
[5 marks]Which type of data are required for the estimation ? Write in details.
[5 marks]Explain the centreline method with suitable example. Figure-1 Figure -
[2 marks]