Write detail specifications for Earthwork in excavation in foundation.
[7 marks]Write short note on Schedule of rates (S.O.R)
[3 marks]Explain in brief about work charge establishment.
[4 marks]Write formulas with their figures, showing the area using hatch, for the following: 1. Area of Segment of Circle. 2. Area of ellipse. 3. Curved surface area of cylinder
[6 marks]Compare,Revised Estimate and Supplementary Estimate
[6 marks]Calculate the followings: 1. No. of bricks required for 1 cu. m. brick work. 2. No. of cement bags for 1 cu.m brick work in cement mortar 1:4
For the Figure-01, find the quantities of following items of work. 1. Earthwork in excavation in foundation trench, 2. Lime concrete in foundation, 3. First class brick work in 1:6 cement mortar in foundation and plinth, 4. 2.5 cm thick DPC (1:2:4) with water proofing compound.
[12 marks]Prepare an abstract sheet for the above quantities.1 FIGURE-01
[8 marks]