Prepare rate analysis for R.C.C. (1:2:4).
Give difference between detailed and brief specification.
[5 marks]Write specification for 12mm thick plaster work in C.M. (1:4).
[5 marks]Write the current market rate for the following items. 1. Cement (per bag) 2. 1st class brick (per piece) 3. Steel (per kg) 4. Mason (per day) 5. 9-inch AAC Block (per piece)
[5 marks]Show the calculation of number of bricks required in 1 M3 brick masonry work.
[5 marks]Write the equation of Area and Volume for the following. 1. Cylinder 2. Frustum of cone 3. Speare 4. Ellipse 5. Frustum of pyramid.
[5 marks]The figure shows a frustum which is obtained by removing a smaller cone with a base radius of 6 cm from the bigger cone that has a base radius of 18 cm. Given that the height of the frustum is 10 cm find its volume.
[5 marks]Enumerates and discuss various types of estimates.
[5 marks]Explain work charge establishment and contingency.
[5 marks]Calculate the followings for fig.-1 1. Excavation for the foundation. 2. B.B.C.C. (1:4:8) for foundation. 3. Brick masonry up to plinth level. 4. Re-Filling of sand in foundation trenches. 5. 5 cm thick D.P.C.1 FIGURE-01