Write the Specification for the 1st class brickwork in CM (1:6) for superstructure.
Define the Rate Analysis and Write down the purpose of it.
[5 marks]Which types of Data are required for the Estimation? Draw the Abstract and Measurement Sheet.
[5 marks]What is mean by ‘Specification’? Enlist and explain the various types of specification.
Find the rate of Plain cement concrete (1:1.5:3) per m3. by rate analysis. Assume suitable rates of material and labour.
Enlist the Different types of Detailed Estimate. Explain any two.
[5 marks]Calculate Area and Volume of the given in figure – 1.
[5 marks]Find the quantity and rate analysis for 100 m2 area and 12 mm thick plaster (1:4).
Prepare the Estimation of following quantities given in fig.2 (Use any Method) 1. Excavation 2. P.C.C 3. 2 nd class brickwork for footings up to plinth level. Figure – 1 Figure -