Prepare a Work Breakdown Structure for a primary school construction.
[3 marks]Draw a bar chart for a below-given project. Also determine total project duration. Activity A B C D Preceding Activity - A A C Duration (Days) 2 4 5
[4 marks]Draw A-O-Anetwork for the below-given project by CPM. Activity A B C D E F G H I Preceding Activity - A A B C E D, F E G, H Q .2 (a ) Differentiate between wheeled mount tractor and crawler mount tractor.
[3 marks]Draw a job layout for commercial complex building construction.
[4 marks]Define the terms: Earliest starting time, Latest starting time, Earliest finishing time, Latest finishing time, Optimistic time, Most likely time, and Pessimistic time.
[7 marks]How to calculate the cycle time of a truck and truck production?
[7 marks]Write advantages and disadvantages of line and staff organization.
[3 marks]Differentiate between activity and event.
[4 marks]Draw a network for the below-given project by CPM. Also determine critical activities, critical path, and total project duration. Activity A B C D Preceding Activity - - A B Duration (Days) 2 4 5
[4 marks]Define with the equation: Mean, Deviation, and Standard deviation.
[3 marks]Represent a Node of a Precedence Network.
[4 marks]Discuss various rules for network drawing.
[7 marks]Why is construction management required in Indian construction industry?
[3 marks]From a drawn cash flow diagram what information can you get?
[4 marks]Explain the steps of cost optimization through the CPM network.1
[7 marks]What is network updating? Why is it important for ongoing project?
[3 marks]Explain economic order quantity in detail.
[4 marks]Explain the step-by-step process of resource smoothening and resource levelling.
[7 marks]Prepare a list of various effects of accidents.
[3 marks]Explain various safety equipment used on construction site.
[4 marks]Explain principles of inspection for quality control.
[7 marks]Write a short note on Tunnel Boring Machines.
[3 marks]Differentiate between a Reciprocating pump and Centrifugal pump.
[4 marks]Draw a neat sketch of truck mounted mobile crane and fixed mast tower crane with all components.
[7 marks]